Project Phases and Schedule
How We Get It Done
The Comprehensive Plan Update was initiated in March of 2026 and will run through four phases until the Plan adoption in May of 2027.
PHASE 1 | LAUNCH
MARCH - MAY
PHASE 2 | FOUNDATIONS & ALIGNMENT
APRIL - SEPTEMBER
PHASE 3 | COMMUNITY ENGAGEMENT
APRIL - DECEMBER
PHASE 4 | PLAN DEVELOPMENT
NOVEMBER - MAY 2027
Establish the Project Management Team
Prepare online engagement & website
Host a community pop-up
Meet with the committee three times
Review City plans and zoning code
Audit the existing Comprehensive Plan
Analyze existing conditions and trends
Launch project website & online engagement
Host stakeholder roundtables (up to eight)
Conduct two public meetings
Compile and summarize public feedback
Compile ideas to create achievable recommendations
Create opportunities for a Future Land Use Map
Create strategies and next steps for effective implementation
Draft Plan document ready to present to City Council for adoption